45,000,000

A Utilities Contract Award Notice
by NETWORK RAIL INFRASTRUCTURE LTD

Source
Find a Tender
Type
Framework (Services)
Duration
5 year (est.)
Value
45M
Sector
CONSTRUCTION
Published
28 Jan 2026
Delivery
To 28 Jan 2031 (est.)
Deadline
n/a

Related Terms

Location

London

Geochart for 2 buyers and 2 suppliers

2 buyers

1 supplier

Description

Network Rail has awarded national Framework Agreements for the provision of Track Bed Investigations for England & Wales, and for Scotland. The framework scope includes standard and deep track bed investigations, concrete coring and various drainage surveys, which are used for the design and specification of the trackbed for track renewals. The framework is specific to the Engineering Services Design Delivery function in Network Rail. The workbank comes from client teams in the Network Rail regions who will call-off from the framework when track bed investigations are required. Due to the work-related nature of these activities, the framework terms & conditions are based on the NR29 Framework Contract for Network Rail Amended NEC4 Engineering and Construction Short Contract. The framework will run for an initial period of five years, and Network Rail will have the option to extend for two further one-year periods, providing the flexibility for a five, six or seven year framework duration.

Lot Division

1 Track Bed Investigation Framework - England & Wales

The specification for the Track Bed Investigation Framework covers the following track bed investigation and associated works, and site & factual reporting which are to be provided for track sites in England & Wales: Standard Track Bed Investigation: • Determining the condition of the existing track bed and sub-grade • Assessing the condition of the existing lineside drainage. • Dynamic Cone Penetration (DCP) to determine the soil structural properties. • Trial trenches to determine drainage paths and lateral variation of track bed materials. • Categorising of Spent Ballast for disposal • Measuring structural constraints (clearances) to support the construction phase and compliance with COM Regulations 2015 (Design Risk Register) to determine construction risks and mitigations. Deep Track Bed Investigation • Deeper window sampling and Standard Penetration Test (SPT) using heavy probing techniques for investigating Track Bed Stabilisation sites. Additional Works and Other Investigation Techniques • Stiffness Measurement surveys using Falling Weight Deflectometer (FWD), and Light Weight Deflectometer (LWD). • Drainage level surveys/topographical surveys to support the design track of drainage systems. • Concrete coring of slab track or other associated foundations • Material testing • Rail and sleeper deflection monitoring using cameras, Geophones or similar.

2 Track Bed Investigation Framework - Scotland's Railway

The specification for the Track Bed Investigation Framework covers the following track bed investigation and associated works, and site & factual reporting which are provided in Scotland: Standard Track Bed Investigation: • Determining the condition of the existing track bed and sub-grade • Assessing the condition of the existing lineside drainage. • Dynamic Cone Penetration (DCP) to determine the soil structural properties. • Trial trenches to determine drainage paths and lateral variation of track bed materials. • Categorising of Spent Ballast for disposal • Measuring structural constraints (clearances) to support the construction phase and compliance with COM Regulations 2015 (Design Risk Register) to determine construction risks and mitigations. Deep Track Bed Investigation • Deeper window sampling and Standard Penetration Test (SPT) using heavy probing techniques for investigating Track Bed Stabilisation sites. Additional Works and Other Investigation Techniques • Stiffness Measurement surveys using Falling Weight Deflectometer (FWD), and Light Weight Deflectometer (LWD). • Drainage level surveys/topographical surveys to support the design track of drainage systems. • Concrete coring of slab track or other associated foundations • Material testing • Rail and sleeper deflection monitoring using cameras, Geophones or similar.

Award Detail

1 Unnamed (None)
  • TBI NR29 NEC4 Engineering and Construction Short Framework Contract - Lot 1
  • Reference: ecm_48952
2 Unnamed (None)
  • TBI NR29 NEC4 Engineering and Construction Short Framework Contract - Lot 2
  • Reference: ecm_48953

Award Criteria

PRICE _

CPV Codes

  • 71631470 - Railway-track inspection services

Indicators

  • Award on basis of price and quality.

Reference

  • FTS 007483-2026