Maintenance and renewal of current lifts, escalators and moving walkways
A Modification Notice
by NETWORK RAIL INFRASTRUCTURE LTD
- Source
- Find a Tender
- Type
- Contract (Works)
- Duration
- 7 year
- Value
- £7M-£20M
- Sector
- CONSTRUCTION
- Published
- 03 Mar 2026
- Delivery
- 01 Mar 2021 to 02 Mar 2033 (est.)
- Deadline
- n/a
Related Terms
Location
London
2 buyers
- Network Rail Infrastructure London
1 supplier
- Schindler Addlestone
Description
This requirement is for the replacement to our current Lifts, Escalators and Moving Walkways Maintenance contract across the NRHS portfolio. This requirement will also include the CP3 refurbishment programme.
Ammendments to Previous Notice
2. Contract value
GBP 11,514,236 20,000,000
Award Detail
| 1 | Schindler (Addlestone)
|
CPV Codes
- 45000000 - Construction work
Indicators
- Contract modified due to additional needs.
Legal Justification
A change of contractor is not feasible following the abandonment of the replacement procurement, which did not result in a viable contract award. No alternative supplier can therefore be appointed within the required timescales. Introducing a new contractor on an interim basis would create unacceptable operational risks for safety‑critical assets, disruption to established maintenance regimes and the need for extensive mobilisation and transition activities across live operational stations. A change of contractor would also result in significant inconvenience and duplication of costs, including parallel mobilisation and demobilisation costs, repeated surveys and asset data capture, training and competence assurance, and transition costs, with no corresponding benefit given the short interim duration pending re‑procurement.
Reference
- FTS 019141-2026