CAL21012 Broadford Primary School - New School

A Contract Award Notice
by THE HIGHLAND COUNCIL

Source
Find a Tender
Type
Dps (Works)
Duration
15 month (est.)
Value
£19M
Sector
CONSTRUCTION
Published
27 Apr 2026
Delivery
To 21 Jul 2027 (est.)
Deadline
n/a

Related Terms

Location

Inverness

Geochart for 2 buyers and 1 suppliers

Description

The Highland Council (THC) is re-developing the primary school at Broadford, Isle of Skye. The new Broadford Primary School (PS) will be built on Highland Council land adjoining the existing school site, and will follow Passivhaus design methods to aid meeting Scottish Government energy targets.

Total Quantity or Scope

2 Stage Tender Procurement.

Award Detail

1 Morgan Sindall Construction & Infrastructure (Motherwell)
  • Num offers: 4
  • Value: £19,457,522
  • Contractor is an SME.

Award Criteria

Quality 40.0
PRICE 60.0

CPV Codes

  • 45000000 - Construction work

Indicators

  • Award on basis of price.

Other Information

The Highland Council (THC) is re-developing the primary school at Broadford, Isle of Skye. The new Broadford Primary School (PS) will be built on Highland Council land adjoining the existing school site, and will follow Passivhaus design methods to aid meeting Scottish Government energy targets. The new school includes the following community elements: · Highland Council Service Point, · High Life Highland Library, and · Enlarged games hall (2-court) to allow for local community use through School Lets process. The new Broadford school with Library and Service Point, will sit within the centrally located Broadford Community Campus that comprises the existing Broadford Village Hall, an existing community grass football pitch, a community play area, and an area earmarked for a new community-funded all-weather pitch (AWP) and changing pavilion. The Library and Service Point will co-locate to the centrally located new school building from the current leased property which is on the outskirts of Broadford. A second new build primary school is being considered for Dunvegan, Isle of Skye. Approval for this new build construction is currently going through due process. If the new primary school for Dunvegan is approved to go ahead, it would be programmed to commence some 3 to 4 months behind construction of the new Broadford primary school. Both schools are of similar design and so the possibility exists, that the selected Contractor for this Broadford primary school project will be considered for pricing the Dunvegan Primary School project. This will only be considered should the selected Contractor be able to demonstrate they are able to price for the Dunvegan primary school project at a pricing level which is similar or below the Broadford primary school pricing levels. (SC Ref:830432)

Reference

  • FTS 038084-2026